Loads to do, but looking good. Thank you Tony and John!
Monday, 27 July 2015
New Facilities Update From The Building Team
Loads to do, but looking good. Thank you Tony and John!
Wednesday, 15 July 2015
New Facilities Project Update
A brief update to the New Facilities Project.

To help with community engagement we will be holding a New Club Facilities Open Day on the Sunday 13th September 11am until 1pm.
Please encourage members of the community to signup for the event at the following address:
https://www.eventbrite.co.uk/e/yeadon-sailing-club-new-facilities-plans-unveiling-community-open-day-tickets-17783368534
YSC members are also welcome to come along and help out.
Bob and Catherine are carrying on the good work looking into funding.
Leonie is working hard on the lease with Howard and Andrew, plus we are also reviewing our CASC status for the project.
John has been doing some great work looking at the plans for the new club house, you will see from this image that considerable effort has been made to visualize the future building.
If you have any questions or feel as though you can help in any way towards our vision, then please email project@yeadonsailingclub.co.uk

To help with community engagement we will be holding a New Club Facilities Open Day on the Sunday 13th September 11am until 1pm.
Please encourage members of the community to signup for the event at the following address:
https://www.eventbrite.co.uk/e/yeadon-sailing-club-new-facilities-plans-unveiling-community-open-day-tickets-17783368534
YSC members are also welcome to come along and help out.
Bob and Catherine are carrying on the good work looking into funding.
Leonie is working hard on the lease with Howard and Andrew, plus we are also reviewing our CASC status for the project.
John has been doing some great work looking at the plans for the new club house, you will see from this image that considerable effort has been made to visualize the future building.
If you have any questions or feel as though you can help in any way towards our vision, then please email project@yeadonsailingclub.co.uk
Facing Facts - Why we need a new Club House and how we plan to achieve it
To explain the what why and how, we have assembled this useful document about facing the facts of a new building project.
Link: Facing Facts - YSC New Facilities Project >
Please share this document.
How You Can Help
Listen to us: Please sign up to our newsletter
Read about us: http://www.yeadonsailingclub.co.uk/project
Follow us: @yeadonsailing
Help us: Tell us If you have services or knowledge that can help us to realise our vision.
Sunday, 28 June 2015
Please support our plans for a new club house with an endorsement!
Saying who we are and what we do is easy for the clubs new facilities project team, but what means more to us are the thoughts and feelings of club members, members of the local community and those from the sailing community.Please help us with a statement of endorsement that we can use in our promotional materials supporting our plans for redevelopment.
If we have inspired you, helped you or made a positive impact that you think the world should know about, then please take a few moments to provide us with a statement of endorsement.
We need your help in upgrading our clubs facilities so we can continue to provide training, racing and social sailing to the Leeds and Bradford area.
Endorse us here.
Saturday, 27 June 2015
Notes from our Funding Meeting
YSC Funding team members held a meeting with representatives from Green Leeds and Leeds County Council regarding funding advice for supporting our build project.
They are extremely knowledgeable in this area having overseen a number of funding applications. They gave Catherine, Bob and myself some excellent advice on how to proceed and information to seek, and we thank her for her time.
Their key message was that in order to have success with applications, YSC needs to be in a strong position to demonstrate community involvement. YSC has been at the heart of the community for a very long time, and is very much part of the community supporting the Tarn Users Forum working closely with other groups to ensure the high standards of maintenance and access to the park and the water.
We will be looking at how we can strengthen our community message, if readers of this blog can suggest any suitable clubs or groups that we can speak to, over and above our current engagement then please email the project team at project@yeadonsailingclub.co.uk
Once again, thank you for giving up their time to meet with us.
They are extremely knowledgeable in this area having overseen a number of funding applications. They gave Catherine, Bob and myself some excellent advice on how to proceed and information to seek, and we thank her for her time.
Their key message was that in order to have success with applications, YSC needs to be in a strong position to demonstrate community involvement. YSC has been at the heart of the community for a very long time, and is very much part of the community supporting the Tarn Users Forum working closely with other groups to ensure the high standards of maintenance and access to the park and the water.
We will be looking at how we can strengthen our community message, if readers of this blog can suggest any suitable clubs or groups that we can speak to, over and above our current engagement then please email the project team at project@yeadonsailingclub.co.uk
Once again, thank you for giving up their time to meet with us.
Wednesday, 10 June 2015
Clubhouse rebuild update - pretty pictures to look at
![]() |
| The dream.. size, shape, and delivery subject to Ts&Cs |
Lease
We are currently discussing the new lease with the council, this discussion has been productive and we hope that we will be able to close this part of the process very soon.
We need a good strong lease which fits with both our needs and the requirements of the funding we will be going for. Thank you Leonie for your efforts on this.
Constitution
We may need to make some standard changes to the constitution to accommodate the funding requirements. We are looking at those tweaks and we will call an EGM soon (potentially on Commodores Weekend). There will be nothing contentious in these changes, but we will need your support in making sure the process is completed in line with the rules of the club.
Planning
![]() |
| Draft layout plan |
And last but not least...
You will notice that this email is signed by Tim Burnett and not Tim Gatti. This is because Tim G has had to make the very sad decision to leave Yorkshire for Norfolk, I'm not sure why because it is flat and only good for growing asparagus :) But it means that he has had to leave the project and I was the lucky one to take this on.
![]() |
| Tim Burnett, in the pub |
If you wish to offer your services, perhaps you are good at bag packing for fund raising? Have good links with local business? Or can rob a bank (just kidding), then we need you. Contact me at project@yeadonsailingclub.co.uk
Sunday, 29 March 2015
Project Kick off
At the AGM before Christmas, the meeting heard that the Club’s original plan to move into the adjacent Leeds Sailing and Activity Centre and share the premises had had to be abandoned partly due to changes in LSAC’s activity levels.
The AGM subsequently adopted a proposal to move towards the development of plans to construct a new Clubhouse facility on our existing site and to raise the necessary funding to enable this to happen.
(This decision was communicated to our local Councillors at a meeting on 21st March 2015 and their sup-port for the Club’s decision was obtained).
As a result, a project structure has been established to progress the various levels of activity necessary to bring this plan to fruition. This project structure can be seen in the right hand navigation.
Four keys areas of work are progressing well:
Lease Extension/Renewal activity
Some of the grants we will be applying for require specific clauses in our lease and a minimum term of ten years. Since the remaining term on our current lease is five years we are in the process of drawing together our requirements for discussion with Leeds City Council to establish a new lease and licence to use the Tarn. A preliminary meeting has already taken place and a second one will be scheduled in April.
Role of Architect
The AGM agreed to allocate Club funds to fund an architect to draw up sketch plans for a new Club-
house, based on our existing wish-list of features and functionality. John Cheetham (a Club member and experienced architect) has been contacted and subsequent discussions have clarified elements of project phasing, roles and responsibilities, fees and timescales for design and construction. John will commence work on the project in early April and sketch plans will be circulated for members consideration in due course. Once these are approved following consultation, we can move towards defining accurate costs and obtaining planning approval.
Funding
Activity is ongoing to develop a funding strategy document as well as further research into sources of grant aid and funding. These include Sport England ‘Inspired Facilities’ funding, grants from Landfill schemes as well as grants from local Councils. We need to secure all necessary funds before we can move onto the demolition and construction phase of the project. Currently we are looking at a total expenditure requirement of around £200K.
Project Management
Tim Gatti and Tim Burnett have been reviewing the most appropriate way to manage the overall project using software tools to enable the team to work together effectively. In the meantime, Tim B has developed a Project Update blog on our new Club website so that members can be kept informed of progress as it happens check it out at www.yeadonsailingclub.co.uk/project
Watch that space!
The AGM subsequently adopted a proposal to move towards the development of plans to construct a new Clubhouse facility on our existing site and to raise the necessary funding to enable this to happen.
(This decision was communicated to our local Councillors at a meeting on 21st March 2015 and their sup-port for the Club’s decision was obtained).
As a result, a project structure has been established to progress the various levels of activity necessary to bring this plan to fruition. This project structure can be seen in the right hand navigation.
Four keys areas of work are progressing well:
Lease Extension/Renewal activity
Some of the grants we will be applying for require specific clauses in our lease and a minimum term of ten years. Since the remaining term on our current lease is five years we are in the process of drawing together our requirements for discussion with Leeds City Council to establish a new lease and licence to use the Tarn. A preliminary meeting has already taken place and a second one will be scheduled in April.
Role of Architect
The AGM agreed to allocate Club funds to fund an architect to draw up sketch plans for a new Club-
house, based on our existing wish-list of features and functionality. John Cheetham (a Club member and experienced architect) has been contacted and subsequent discussions have clarified elements of project phasing, roles and responsibilities, fees and timescales for design and construction. John will commence work on the project in early April and sketch plans will be circulated for members consideration in due course. Once these are approved following consultation, we can move towards defining accurate costs and obtaining planning approval.
Funding
Activity is ongoing to develop a funding strategy document as well as further research into sources of grant aid and funding. These include Sport England ‘Inspired Facilities’ funding, grants from Landfill schemes as well as grants from local Councils. We need to secure all necessary funds before we can move onto the demolition and construction phase of the project. Currently we are looking at a total expenditure requirement of around £200K.
Project Management
Tim Gatti and Tim Burnett have been reviewing the most appropriate way to manage the overall project using software tools to enable the team to work together effectively. In the meantime, Tim B has developed a Project Update blog on our new Club website so that members can be kept informed of progress as it happens check it out at www.yeadonsailingclub.co.uk/project
Watch that space!
Subscribe to: